Order Feasibility

Before quoting: technical fit, material, capacity and the delivery date the plant can make, estimated cost and margin, payment terms and the cash the order ties up — and the bid / no-bid decision, approved.

What changed in Order Feasibility recently

  1. New · Release 2.31 · 19 November 2026

    Opportunities & RFQs, Quotations and Order Feasibility: each open RFQ shows its win chance at the quoted margin and its expected value, from a curve fitted on this plant’s own decided quotations and back-tested against the plant’s win rate. Where the curve does not beat the win rate, the win rate is shown and Quotations recommends no margin from the curve. Order Feasibility records won or lost on a bid, and shows the win chance and expected profit at the assessment’s margin beside the rules, which still decide.

  2. Improved · Release 2.13 · 15 November 2026

    Order Feasibility plans a material imported for an order at the typical lead time from its country — about 30 days from North Europe, 22 from the western Mediterranean, 19 from the eastern Mediterranean and Türkiye, 45 from Asia — from the supplier’s dispatch to the plant. A planner’s lead time or one set under Terms & assumptions still comes first.

  3. Fixed · Release 2.06 · 15 November 2026

    A second pass fixed more figures at their source: first-pass yield is weighted by value (products are counted in different units — 95.6% for all plants, not 97.3%); MRP and Procurement count only stock that can be issued (34 materials short within 30 days, not 27); raw stock is aged receipt by receipt; Cash Planning rolls an entered balance forward from its date; recorded stops count against planned shift time only; fabrication progress is weighted by each stage’s planned hours; Order Feasibility prices materials at the product’s standard cost; budget forecasts never count open orders twice; and a Riyadh-only view reads in riyals on Suppliers and Raw materials.

  4. Improved · Release 1.90 · 13 November 2026

    Order Feasibility pays each material at its supplier’s set terms and the balance at the named customer’s, each marked set or assumed; with nothing set, it assumes the same 60-day supplier terms as Supplier Bills and Cash Planning.

  5. Improved · Release 1.86 · 13 November 2026

    A record’s own terms still come first; otherwise the value set here dates invoices, supplier bills, purchase orders and the cash plan, and Working Capital ages the plants’ invoices and bills the same way. Until one is set, the default shows, labelled assumed, with a Set link beside it on Invoices, Supplier Bills and Order Feasibility.

  6. Improved · Release 1.86 · 13 November 2026

    Order Feasibility uses each short material’s set lead time and the set CBE rate (the planner’s own lead time on a check still wins); the sample feasibility studies take the set tax, discount and inflation rates.